Using our technology and our heritage of experience and expertise, we were able to built this dam entirely in our workshops. It is part of the equipment used at a hydroelectric plant, and our solution made it possible to attain maximum rapidity of installation, necessary in this case because of the river's particularly high flow rate. In just two days, our customer was able to put the power generation plant into action.
SCHEDA TECNICA | |
Località: | Lomello (PV) |
Corso d'acqua: | Torrente Agogna |
Tipo: | Hard -Top |
Uso: | Sabrramento per opera di presa |
Potenza impegnata: | 3 Kw |
Lunghezza complessiva: | 26 m |
Altezza: | 0,80 m |
Gonfiamento: | ARIA |
Tempo di gonfiamento: | MAX 15 min |
Tempo di sgonfiamento: | max 25 min |
Caratteristiche della centrale elettrica | |
Salto complessivo: | 2,80 m |
Incremento di salto: | MAX 0,80 m |
Portata derivata: | MAX 25 m3/s |
Turbina: | N.3 COCLEE Generatore: N.3 AD ASSE ORIZZONTALE + INVERTER |
Potenza alla rete: | max 270 kW |